Current Status

Bhoomi Pooja

08-09-2023

08-09-2023

Piling Work - Test Pile Activity

07-03-2023

07-03-2023

Machinery Engaged for the Piling Works

21-03-2024

01-05-2024

Piling Works

03-05-2024

19-06-2024

Piling Works - Pile Drilling and Hard Rock Samples

15-02-2024

27-02-2024

Core Barrel bit for Uplift piles with socketing 1.7D anchoring in hard rock

04-04-2024

04-04-2024

Piling Works - Steel casing insert by vibro hammer mechanism

23-01-2024

23-01-2024

Piling Works - Steel reinforcement works for piling

20-12-2023

19-01-2024

Piling works - Concrete works

04-04-2024

04-04-2024

Piling works- Quality assurance by cube casting and testing

24-04-2024

24-04-2024

Erection of In-house Batching plant for the project

26-01-2024

26-01-2024

Pile chipping works

26-04-2024

26-04-2024

Piling works - Pile Integrity test and Dynamic load test

09-02-2024

30-04-2024